Work in Process

Pinellas Heights Senior Apartments Update

By April 15, 2014 No Comments

Work continues at Pinellas Heights Senior Apartments in Largo, Florida.  All site rough grading is now complete and the underground site utilities are getting tested to be put in service.   The South half of the precast floor plank for the third floor has been set and have  the third floor masonry walls have been started.   Metal framing in the first floor residential units has begun, and Mechanical, Plumbing, and Fire Sprinkler subcontractors have started their rough-in work.